A Logical Approach to Safety Stock, Without Statistics

dandoodlescan065-inventory is wasteIn it's entry on Safety Stock, Wikipedia states that some of the more common reasons for safety stock include:
# Supplier may deliver their product late or not at all
# The warehouse may be on strike
# A number of items at the warehouse may be of poor quality and replacements are still on order
# A competitor may be sold out on a product, which is increasing the demand for your products
# Random demand (in reality, random events occur)
# Machinery Breakdown
# Unexpected increase in demand

There are many reasons and methods for calculating safety stock, and one of the more common reasons I've seen in the world of complex electronic assemblies is Test Yield. As electronic assemblies get more complex due to smaller component packages and denser placement on the board, as well as tougher requirements for the boards themselves, there will always be issues with yield. Couple this with complex testing requirements for certain high-reliability electronic assemblies, and yield issues begin to multiply. While zero defects is the goal we all strive for through continuous improvement programs, the real world has to take defects into account. Along with the actual defect comes accounting for the turnaround time to troubleshoot and repair boards, and finally, accounting for the loss of irreparable assemblies.

It might be easy to say "Well, I'll just take whatever my first-pass fall-out is and release that many more in each work order". But, releasing extra quantities in each work order isn't safety stock; safety stock is the quantity of units required in your supply chain to account for VARIANCE and achieve your target service levels to the demands from your customer. While there are statistical formulae to determine order quantities and safety stock, if you understand your planning factors and your processes, you should be able to model your order quantities while achieving inventory and service goals.

Depending how the planning factors are set in your materials requirement planning (MRP) module, you won't be releasing the same quantity in each work order. Most MRP systems will "see" those defective units unless they are immediately placed in an inventory status that "blocks" MRP. If your processes allow for defective units to sit in WIP through the next MRP cycle, your planned orders will be reduced accordingly.

For the example below, I assumed a first-pass yield of 97% and a scrap rate of 0.5%. Another factor that is important in the cycle below is that the test occurs on Day 5 of a 5-day cycle and it takes 2 days to troubleshoot and repair the units, which means the units show in WIP at the time of the next order release. See this example:































Manufacturing Lead Time (days)5
Weekly Demand100
Historical First-Pass Yield97%
Historical Final Yield99.50%
Historical Troubleshoot & Repair Time (days)2
Day Test Occurs5
Initial Order Qty + Safety Stock103

















































































Wk 1Wk 2Wk 3Wk 4Wk 5Wk 6Wk 7Wk 8Wk 9Wk 10
Demand100100100100100100100100100100
Order Release103100101100101100101100101100
Order Shipment100100100100100100100100100100
Fallout/Scrap11111
Balance in Troubleshoot WIP3232323232


As you can see, the quantity of units in WIP from one cycle to the next fluctuates between 2 and 3 units - 2%-3%.

There will be some in your organization (for instance, the production supervisor ;-) ) suggesting you should always release 103 units in each work order. Not only are they wrong, doing so will actually drive up your work-in-process (WIP) inventory - a cerain percentage of your first-pass defects will go through a troubleshoot-and-repair cycle, making them available for finished good shipments. If you continue to release "X" extra in each work order, WIP inventory builds according to this formula:

(Units released) + (Units Repaired) - (Shipments)

In the example above, watch what happens to your WIP inventory:

















































































Wk 1Wk 2Wk 3Wk 4Wk 5Wk 6Wk 7Wk 8Wk 9Wk 10
Demand100100100100100100100100100100
Order Release103103103103103103103103103103
Order Shipment100100100100100100100100100100
Fallout/Scrap11111
Balance in Troubleshoot WIP35810131518202325


As you can see, your inventory will build to infinity unless some undefined variable consumes these units. Obviously, this is not a satisfactory solution in any organization due to the impact his has on cash flow.

These examples are simple and focus only on one variable - Yield. In a robust safety stock model one would account for other sources of supply and demand variance - forecast accuracy, supplier performance, additional quality yields, etc. But the examples do demonstrate how one can easily get to a safety stock determination through logical thinking, an understanding of their internal processes, and simple math.

I would love to see other examples of how to account for variance in the supply chain, so please leave me a comment if you care to continue the conversation.